Strengthening Harbour Resilience: LHI’s 3D Physical Modelling Solutions for Gandara Fishery Harbour
26th October 2026
Lanka Hydraulic Institute Ltd (LHI) completed the “Physical Model Study for Evaluation of Harbour Modification Options to Assess Wave Disturbance and Beach Stabilization at Gandara Fishery Harbour” for Ministry of Fisheries, Aquatic and Ocean Resources (MFAOR) of Sri Lanka. The consultancy commenced in December 2025 and concluded in June 2026.
In response to the high wave disturbance and erosion of the outer basin’s beach landing area observed under extreme wave conditions, the Ministry proposed harbour modification options incorporating combinations of a proposed outer breakwater, an inner breakwater and an inner groyne. LHI was commissioned to evaluate these options through scaled testing at its 3D physical modelling facility. LHI’s wave basin supports investigations of harbour tranquillity, wave penetration, structural stability and sediment behaviour.
Gandara Fishery Harbour experiences substantial wave disturbance near the quay walls and within the inner harbour basin, alongside erosion of the beach landing area in the outer basin. Exposure to long-period swell, particularly during the southwest monsoon, affects berthing, mooring and beach landing operations. Overtopping of the main breakwater was another concern identified during field observations and stakeholder consultations.
These issues required a study of how the proposed structures would modify wave penetration, harbour calmness, navigation conditions and beach stability.
The main objective was to identify the most suitable modification options among the Ministry’s proposed layouts under four specified representative wave conditions. Following client-requested revisions, LHI tested ten configurations, including the existing harbour and an intermediate construction arrangement, under controlled conditions at mean sea level.
The study assessed wave disturbance in operational areas and at the harbour entrance, main breakwater overtopping, stability of proposed structures, and erosion and accretion at the beach landing area.
The study identified harbour modification options that substantially reduced wave disturbance and improved protection of the beach landing area. Following technical review and stakeholder consultations, a preferred layout was agreed, considering engineering performance, construction costs and the needs of both multi-day and single-day fishermen. The agreed construction sequence prioritises the outer breakwater, followed by the inner breakwater. The findings provide a practical basis for implementing improvements to support safer berthing, mooring and beach landing operations. Operational precautions remain necessary during high-wave events, with travel lift operations recommended only under calm conditions.
Established in 1984, Lanka Hydraulic Institute Ltd (LHI) combines coastal engineering expertise with physical and numerical modelling and field investigations to support fisheries infrastructure development in Sri Lanka and overseas. Central to these capabilities is LHI’s hydraulics laboratory, equipped with a 3D wave basin and 2D wave flume for testing harbour layouts and marine structures under controlled wave conditions.
LHI’s 3D physical modelling facility enables engineers to investigate wave penetration, harbour tranquillity, breakwater stability, overtopping and sediment behaviour.
LHI’s broader consultancy experience encompasses fishery harbour development and improvement projects throughout Sri Lanka, including Wellamankara in Wennappuwa, Hikkaduwa, Ambalangoda, Cod Bay, Valaichchenai, Hambantota, Kalametiya, Kudawella, Puranawella, Mirissa, Beruwala, Panadura, Mutwal, Dikkowita, Kapparatota and Balapitiya. Depending on project requirements, its services have included feasibility studies, field investigations, numerical and physical modelling, detailed engineering design, contract administration and construction supervision.
Internationally, LHI has undertaken 2D and 3D physical modelling studies for major port and coastal infrastructure projects in South Korea, India, France, the Maldives, Oman and Algeria. Its fisheries-related modelling portfolio includes studies for fishery harbours at Mahout, Shuwamiya, Sadah, Rakhyut, Dibba and Kumzar, as well as fish landing centres at Darsait, Aint, Al Fazayah and Haramel in Oman. LHI has also provided design and engineering consultancy for the Lakbi and Hadbin fishery harbour and fish landing centre developments in Oman.
The completed Gandara study demonstrates the application of this specialist modelling expertise to Sri Lanka’s fisheries sector, providing an evidence-based foundation for selecting practical harbour modifications that address wave disturbance, beach landing erosion and the operational needs of fishing communities.